Study of factors affecting construction cost performance in Jalingo Taraba State

Study of factors affecting construction cost performance in Jalingo Taraba State

@SparklynServices
WhatsApp Channel

DEDICATION

This research material, titled “Study of factors affecting construction cost performance in Jalingo Taraba State” is dedicated to God for His boundless grace and guidance. It is also a tribute to all computer enthusiasts whose contributions made my research journey smoother and enriched my documentation process, making the experience truly fulfilling.




ACKNOWLEDGEMENT

I am profoundly grateful to everyone who contributed to the successful completion of this project. I am especially grateful to my Supervisor (Name), the Head of Department (Name), and the Lecturers in the Department of Building Technology (BT) for their invaluable guidance and support. I also acknowledge the contributions of authors and scholars whose works on Study of factors affecting construction cost performance in Jalingo Taraba State provided essential insights. Special thanks go to my study area (and any funding organizations, if applicable) for their financial assistance. I am equally thankful to stakeholders, including mentors, teachers, and colleagues, for their encouragement and support. Finally, I deeply appreciate my family and friends for their patience and unwavering support throughout this journey. Your contributions have been instrumental in making this research a reality.




PRELIMINARY PAGES


CHAPTER ONE

INTRODUCTION

  • 1.0 Introduction
  • 1.2 Aim and Purpose of Study
  • 1.3 Statement of Problem
  • 1.4 Research Approach
  • 1.5 Limitation of Study
  • 1.6 Significance of Study
  • 1.7 Definition of Terms

CHAPTER TWO

LITERATURE REVIEW

  • 2.1 Introduction
  • 2.2 Budget Planning and Control
  • 2.2.1 Traditional Procurement
  • 2.2.2 Management Procurement
  • 2.2.3 Integrated Procurement
  • 2.2.4 In House Procurement
  • 2.3 Cost Performance is the Fundamental Norm of Measuring Project Success
  • 2.4 Construction Site
  • 2.4.1 Types of Construction
  • 2.4.1.1 Residential Building
  • 2.4.1.2 Institutional and Commercial Building
  • 2.4.1.3 Specialized Industrial Construction
  • 2.4.1.4 Infrastructure and Heavy Construction
  • 2.5 Performance in the Construction Industry
  • 2.5.1 Contractual performance
  • 2.5.2 Performance specification
  • 2.5.3 Performance bond
  • 2.6 Definition of Time and Cost Performance
  • 2.6.1 Time Performance
  • 2.6.2 Cost Performance
  • 2.7 Time Variance for Water and Sanitation Projects
  • 2.7.1 Bromilow’s Time-Cost Model
  • 2.8 Problem of Performance in Construction Industry
  • 2.9 Project Management and Performance

CHAPTER THREE

RESEARCH METHODOLOGY AND THE STUDY AREA

  • 3.1 Introduction
  • 3.2 Research Methodology
  • 3.3 Questionnaire
  • 3.3.1 Questionnaire Design
  • 3.4 Study Population
  • 3.5 Data Requirement
  • 3.6 Sample Frame
  • 3.7 Sampling Techniques
  • 3.8 Data Collection and Analysis
  • 3.9 Data Collection Instrument
  • 3.9.1 Administration of Questionnaire
  • 3.9.2 Personal Interview
  • 3.9.3 Personal Observation
  • 3.9.4 Relevant Publication

CHAPTER FOUR

DATA COLLECTION, ANALYSIS, PRESENTATION AND INTERPRETATION

  • 4.1 Introduction
  • 4.2 Classification of Jalingo, Taraba State (JTS) Projects
  • 4.3 JTS Construction Procurement
  • 4.4 Factors Affecting Construction Cost Performance
  • 4.4.1 Fluctuation in Prices of Materials
  • 4.4.2 Cash Flow and Financial Difficulties Faced by Flow and Financial Contractors
  • 4.4.3 Shortage of site workers
  • 4.4.4 Lack of communication between parties

CHAPTER FIVE

SUMMARY OF FINDINGS, RECOMMENDATIONS AND CONCLUSION

  • 5.1 Summary of findings
  • 5.2 Recommendations
  • 5.3 Conclusion

REFERENCES

APPENDIX



ABSTRACT

Maintaining steady cost projection on construction projects had been until recently an issue of serious concern, both to the client and project contractors. Cost deviation from initial Cost plan, had been prevalent on Construction sites. However, little or no efforts has made to curtail the phenomenon, it is against this background that this research work attempt to study the factors that are responsible, so as to identify them and proffer possible ways of tackling the menace. The study attempt this through chosen construction practitioners as population and samples were drawn to this effect at random from the category of professionals, using probability sampling methods. The Data were collected from primary source consisting of structured questionnaire designed in Likert Scale in rating Scale of 1 to 5, while the Secondary Data were collected through review of Journal articles and relevant Text books. The Data were analysed using Severity Index, Ranking and Simple Percentages. It was discovered from the analysis that factors such as Contractors inexperience, inadequate planning, Inflation, incessant variation order, and change in project design were critical to causing cost overrun, while project complexity, shortening of project period and fraudulent practices are also responsible. The study concluded with recommending, adequate planning using conventional techniques, Studying and applying project history, material bulk purchase, proper project design and establishing proactive fraud prevention system on sites, as panacea for effective cost performance on sites.



Study of factors affecting construction cost performance in Jalingo Taraba State


1.0 Introduction

Construction industry in Nigeria had been a major source of employment for 70% of labour force in the country, thus it controls the capital flow, as well as labour resources, which has cost implications. Adequate management of these resources is considered an important aspect of project works; it determines to a large extent the overall success of project works. So also if the resources are adequately harnessed, issues that pertains to cost overrun would not arise which could result to variations and claims.

Some firms rely on claim as a result of variation incurred during the course of the Project execution and afterward evaluate their profit after incurring necessary and unnecessary cost on a project. This however has tendency of positioning such in a disadvantageous profit position. An effective cost management strategy is therefore necessary, this could be achieved through putting in place a proactive cost management strategy (Love et al, 2005; Ogunsemi and Jagboro, 2005; Ferry et al, 1998).

They described cost management system as a process that should be carried out throughout the life cycle of a project, from the inception to final completion and final payment to the contractor. In the light of this, the timeliness and cost effectiveness of various operation and decision carried out will determine to an extent the magnitude of cost that could be saved on the project. ( Kerzner, 2005; Ogunsemi and Jagboro, 2005).

However Dissanayaka and KuJTSswamy(1999) opined that Time, Cost, Quality target as well as project satisfaction tend to be most important key to measure the overall performance of a project work. Furthermore, various research works have also indicated that most project records cost or time overrun during their tenure of execution.( Odusami and Olusanya, 2000). (Mbachu and Olaoye, 1989; Madewsley, et al, 2004); opined that 51percent of average delay were experienced yearly which culminates in cost overrun, certain factors are responsible for this, to this end however this study attempts at investigating such factors and proffer solution to the pandemic. The scope of this research work shall be limited to building construction sites within the selected area in Nigeria, Ogun state, Lagos state and Northern part of Nigeria. This is attributable to unique project environment they possess. The aim and Objectives of the research are as follows:

The research work is to determine the various factors that interplay in impacting project cost performance, investigating the order of severity of the factors, and recommending ways of curtailing the effects. Field survey was carried out with 100 questionnaire distributed and 67 were used for analysis of response from construction practitioners selected randomly from population of construction firms, The primary data were collected with the aid of structured questionnaire designed on Likert Scale of 1to 4 rating scale. Mean item score, Simple percentages and severity index were used as analytical tool of the generated data. SPSS (Statistical Packages for Social Science Students) was used in determining pattern of relationship among the cost determinants and variables. The factors were ranked in order of their degree of severity. It was discovered from the findings that, these factors are the major ones that results in cost overrun on construction sites.

  • Inadequate planning
  • Contractors project inexperience
  • Inflation
  • Incessant variation order
  • Change in project design
  • Project complexity
  • Shortening of contract period and
  • Fraudulent practices.

In order to prevent occurrence of cost overrun or a practice action towards prevention of such, the following are recommended.

  1. Inadequate planning: breaking of project planning into short term achievable goals, medium term planning and Long term planning
  2. Studying of project history for possible application on another similar projects
  3. Bulk purchase of material
  4. Proper design of the Project during design stage so as to avoid. Undue on-project variation
  5. Establishing fraudulent detecting system or system of individual accountability to discourage pilfering, stealing and other related vices.

1.2 Aim and Purpose of Study

This study has focused on investigating procurement strategies adopted in Jalingo, Taraba State large construction projects. It also identified various factor affecting construction cost performance of Jalingo, Taraba State large construction projects.

Purpose of Study

Very rarely Jalingo, Taraba State projects are finished within estimated project cost. For improving cost performance, it is very important to identify the reasons affecting cost performance of Jalingo, Taraba State projects. Hence, there is a need of study in understanding the reasons and factors affecting project cost performance of construction projects.


1.3 Statement of Problem

This study revealed that;

  1. Fluctuation in price of the material,
  2. Cash flow and financial difficulties faced by contractors,
  3. Shortage of site workers,
  4. Lack of communication between parties,
  5. Incorrect planning and scheduling by contractors

Are most severe factors while frequent design changes and owner interference are least affecting factors on construction cost performance in Jalingo, Taraba State large projects.


1.4 Research Approach

The project was carried out through interviews and survey using the questionnaire among the personnel involved in handling Jalingo, Taraba State large projects. Gathered data was analyzed statistically using SPSS software package.


1.5 Limitations of the Study

This study was limited to large construction projects administrated by Jalingo, Taraba State. During the course of this study, many things militated against its completion, some of which are:

  1. Time Constraint: The time frame given to accomplish this project was very short due to school academic calendar and it was carried out under pressure which made the researcher not to implement some necessary features.
  2. Establishment Policies: Establishment policies posed a serious limitation as most staffs are not ready to release information needed for this project work. There were lots of information needed from the staffs of this institution to enhance the study which took them time to release or they did not release at all for security purposes, hence the scope was reduced.

1.6 Significance of Study

This study has highlighted various issues causing poor project performance in Jalingo, Taraba State large projects. Ranking of the factors will enable the Jalingo Taraba State engineers for taking appropriate actions in improving the performance of cost in construction projects.


1.7 Definition of Terms

Builder: this is a professional in which is responsible for hazardous translating and developing all designs by other consultants.

Culture: this is defined as the total way of peoples life in terms of attitude benefits, perceptions, values and morality.

Management: It is the discipline of planning co-coordinating, organizing, controlling, leading, forecasting, securing and managing resources to being about the successful completion of specific project goals and Objectives.

Architects: this is a professional in the field of architecture who design building plan and supervision.

Construction: according to Wikipedia's encyclopedia construction is designed as a process of assembling of infrastructure and consists of building up of several activities into final project.

Project: it is a temporary endeavor having a defined beginning and end which is an undertaken to meet unique goals and Objectives.

Building Construction: it is the process off aiding structure to real property.

Building: It is defined as a structure erected where it is to stand with the main functions of shelter and habitation for man.

Project Manager (PM): is the person accountable for accomplishing the stated project Objectives.

Project Management (PM): This is field of study or discipline of planning organizing securing and managing resources for a successful completion of project within the stipulated time to meet its desired goals and Objectives.

Project Proposals (PP): They are documents designed to present a plan to action.

Quality: The general standards or grade of something it also means the highest of finest standard.

Management: this has to do with the ways and pattern in zerock construction organizer, plan, and control and managed all site and construction administration.

Project: is a temporary effort to create a unique product or several which the building construction that has to be done by Zerok construction without unnecessary delays and on time too.

Clients: proper funding will assist Zerock construction to execute their work effectively.

Structural Engineer: should ascertain that the correct size and type of reinforcement bar is used for each project to discourage collapse.

Quantity Surveyor (QS): As a cost analyst, the QS must ensure that the bill of quantities (BOQ) is adequately prepared for good quality project by Zerock construction Nigeria limited.

Site: it is the central point of all construction activities.


CHAPTER TWO

2.0 Literature Review

2.1 Introduction

This chapter focuses on the review of related literature. A literature review includes the current knowledge as well as theoretical and methodological contributions to a particular topic. It documents the state of the art with respect to the topic you are writing. It surveys the literature in the topic selected. In this research work the literature review includes the conceputal review, theoretical framework, the review of related literature …

Procedure for Accessing and Downloading the Complete Material in PDF or DOCX Format

Above is a preview excerpt of the full study on “Study of factors affecting construction cost performance in Jalingo Taraba State”. The complete material, including all five chapters, is available for download upon request.


To obtain the complete research material content, simply place an order by paying the specified project or seminar fee using the account details or electronic payment (E-payment) system provided below.


Seminar Material
₦3,000
Project Material
₦5,000

For Mobile Money (MoMo) and Researchers Outside Nigeria, Kindly Request Complete Material via WhatsApp.


Account Details - For USSD / POS Transfer

ACCT NAMESPARKLYN SERVICES
Zenith Bank PLC1222599051
MoniePoint (MFB)8030511988
Paycom (OPay)8030511988

–– or ––



After payment, send message containing your payment receipt to Sparklyn Services with the phone number displayed below.


Once payment is confirmed, the complete document will be delivered via WhatsApp or email in Microsoft Word (MS-Word) format.




You can get more research topics on Building Technology, if you did not see your preferred topic from the alternate list above.

Defense Procedure for Building Technology Researchers


In preparation for defending a project or seminar on Study of factors affecting construction cost performance in Jalingo Taraba State, it is imperative that as a nursing student, you demonstrate comprehensive knowledge of your research. The defense process is structured to include presenting your work, answering questions, and illustrating its pertinence. Initially, provide a succinct yet thorough introduction to your research topic, emphasizing its importance and the objectives, ensuring that both the audience and the External Examiner can understand the scope of your study.


Prior to your defense, be thoroughly acquainted with your research abstract and the critical elements of Chapter One, including motivation for embarking on this research, problem statement, objectives, and significance. In Chapter Two, be ready to cite at least two references from the literature review. For Chapter Three, you should be equipped to discuss the methodologies, tools, and techniques utilized. In Chapter Four, defend your research by justifying the findings and linking them to your research objectives.


Conclude your defense by succinctly summarizing the study and offering insightful, evidence-based recommendations. A professional dress code, such as wearing a suit and tie, is vital to create a favorable impression and elevate your presentation.


During the question and answer segment, the External Examiner may pose questions pertaining to your research. If confronted with a challenging or irrelevant question, respond diplomatically with, “Sorry, Sir/Madam, the question asked is beyond the scope of my study.” Whenever possible, direct your answers back to your research findings to reinforce your expertise.